Toronto building inspections and closing an open permit
Toronto, Ontario, Canada
A Toronto building permit stays open until required inspections are completed and the city closes it.
Key information
A Toronto building permit stays open until required inspections are completed and the city closes it. Book each mandatory stage before covering the work, and arrange a final inspection when construction is done.
On this page
Next step by project status
| Situation | Required action |
|---|---|
| Work recently completed | Request final inspection |
| Work started but unfinished | Request progress inspection and follow directions |
| Work never started | Request permit revocation |
| Work finished without inspections | Final inspection and possible engineer/architect reports |
| Previous owner’s work still open | Current owner must resolve it; transfer if continuing work |
Sources: Closing Building Permits
From booking to a closed permit
- Book
Provide the permit number and the on-site contact. A voicemail still needs an agent callback.
- Expose and inspect
Keep the work visible and permit plans available. Correct any deficiencies.
- Close
Complete all required inspections and obtain city confirmation of closure.
Sources: Request a Building Inspection
Online and telephone booking
The inspection portal is available 24/7 to request, cancel or reschedule. Supply the permit number and contact details of the person meeting the inspector. Inspection visits are weekdays 8:30 a.m. to 4:30 p.m., excluding holidays.
The city allows requests from the next business day up to four weeks ahead. The inspector contacts the applicant on the selected day to arrange a visit that day or the next. A requested date is not an exact arrival appointment.
The request page lists 416-338-0700 for an agent. Leaving voicemail is not a completed booking; an agent must call back to collect required information. The closure page separately lists 416-397-5330 and TOBldgInsp@toronto.ca for open-permit matters.
Sources: Request a Building Inspection · About Building Inspections · Closing Building Permits
Prepare the site and drawings
The inspector must see the relevant construction. Work covered before its mandatory inspection may have to be uncovered. Keep all permit documents and specifications on site, including a full-scale colour print of approved drawings when requested.
The permit documents name the inspector and contact office. Ask that inspector which stages apply to the specific work. Mandatory inspections are included in the permit fee; extra inspections may attract a separate charge. A status report is a separate request and cannot be ordered through the inspection-booking function.
Sources: About Building Inspections · Request a Building Inspection
Inactive permits and previous owners
The city issues a Notice of Intention to Revoke where a permit is over 18 months old with no inspection request. It is not yet a revocation, but ignoring the stated deadline can lead to one. To keep the permit open, request inspection and show construction genuinely started.
A buyer becomes responsible for unresolved permits from earlier owners. Determine whether any work occurred. If continuing that work, apply for a transfer. If completed without inspections, the city may require professional reports. Revocation does not certify uninspected work as safe, and restarting can require a new application and fees.
Sources: Closing Building Permits
Questions and answers
Does finishing the building automatically close the permit?
No. Schedule the final inspection and receive city closure confirmation.
Source: Closing Building Permits
How far ahead can I request an inspection?
From the next business day to four weeks ahead.
Source: About Building Inspections
Is the chosen date a precise appointment?
No. The inspector contacts you on that day to arrange the same-day or next-day visit.
Source: About Building Inspections
Can I leave voicemail and assume it is booked?
No. An agent must call back and collect the required details.
Source: Request a Building Inspection
Can I cover walls before the mandatory inspection?
No. Covered work may need to be uncovered for inspection.
Source: About Building Inspections
Are mandatory inspections charged separately?
They are included in the permit fee; additional inspections may cost extra.
Source: About Building Inspections
Does an inspection portal request buy a status report?
No. The online booking function cannot request an Inspection Status Report.
Source: Request a Building Inspection
What does a Notice of Intention to Revoke mean?
The permit can be revoked on the letter’s date if you do not respond and demonstrate progress.
Source: Closing Building Permits
Who resolves a previous owner’s permit?
The current registered owner.
Source: Closing Building Permits
What if no work ever began?
Request revocation instead of treating the unstarted project as completed.
Source: Closing Building Permits